The EPC manager of a USD 10 billion-plus airport project faced an ICC arbitration brought by the owner after significant delays and cost overruns. Completion had taken more than three times longer than planned, and the owner sought more than USD 1 billion in financial compensation.
Our work helped the Tribunal focus on the packages, sequences and project-management events that mattered most to the delay case. Under cross-examination, the analysis provided a structured way to test a highly fragmented project record against the respondent’s position.