Our team converted the project data into structured delay and quantum analyses, isolating critical and near-critical paths through key process units and testing causation using programme, progress and commissioning records. In parallel, we assessed cost claims against supporting documentation, identifying unsupported amounts, duplication and gaps in substantiation. The resulting analyses were prepared for use in expert reports, hearing demonstratives and oral testimony.