Our client, the EPCM of a $10bn+ airport project with over 100 Contract Packages, faced significant delays and cost overruns, with completion taking more than three times longer than planned. We were appointed to prepare an independent expert report for ICC Arbitration.
Our analysis helped define critical contract packages, guiding our client’s strategy and showing where efforts should be focused. We highlighted engineering, procurement and project management issues and identified where additional technical experts would be required, strengthening our client’s position during arbitration.