Bringing structure and independence to overlapping construction claims across a major development

Situation : Différends
L'arbitrage

Contexte

A large-scale Middle Eastern development programme involved multiple legacy claims amounting to several billion dollars across multiple contractors, packages and dispute workstreams, with overlapping delay and quantum issues.

Principaux enseignements

Our analysis enabled stakeholders and decision-makers to distinguish supported claims from unsupported assertions. It provided a consistent, independent framework for negotiation, dispute resolution and, where required, expert evidence capable of withstanding Tribunal scrutiny and cross-examination. The close collaboration of our delay and quantum teams enabled us to consistently deliver robust and coherent findings.

Rôle de précision

Our experts separated the claims into defined packages and delay windows, testing each narrative against the contemporaneous record through critical-path reviews, claim-event mapping and quantum substantiation analysis. The findings were translated into practical, structured materials for decision-makers, legal teams and dispute proceedings.

Partager